Creating a CornerStone® reinforced retaining wall system, involves the use of geogrids for reinforcement. Cornerstone geogrid retaining walls 3.5ft (1.07m) and taller will automatically have active pressures because of their height. Retaining walls smaller than 3.5ft (1.07m) may also require geogrid reinforcement depending on other related factors. Parking lots, roadways, or positive slopes above walls for example, require the use of reinforcement to help resist the increased pressure behind the wall. Geogrid used with the appropriate lengths, layers, and compacted backfill materials will resist these active forces above and behind the wall. For CornerStone 100 geogrid reinforced retaining wall  3.5ft (1.07m) and taller a qualified engineer should be consulted.

Step 1: Planning Your Retaining Wall

  • Excavate and prepare Sub Base Leveling Trench 6″ below first course
  • Leveling Pad Trench is approximately 2.5′ to 3′ wide
  • Normal wall Burial Depth or Embedment Depth is 6″ to 12″ or one block (for more information refer to design manual)
  • Excavate cut line to a 2 to 1 slope or greater
  • Back of retaining wall excavation depth into the bank at the base of the wall should be from the face of wall to the designed length of Geogrid

Step 2: Cut Geogrid for retaining wall

  • Cut Geogrid Reinforcement to the length specified in the design
  • Geogrids are manufactured in two directions Uni-axial or Bi-axial. Uni-axial grid has one direction of strength and that direction has to be oriented perpendicularly to the face of the wall during installation. Bi-axial grid can be laid in two directions, perpendicular and lengthwise to the face of wall (ensure that the lengthwise direction is still in accordance to the length specified by the Engineer’s design)
  • Correct geogrid orientation, strength and length is crucial to the success of the retaining wall project
  • Each geogrid length should be laid parallel and adjacent to each other but never overlapping

Step 3: Lay Geogrid

  • Place the geogrid as far forward on the CornerStone® units as possible without revealing it on the face
  • Place the next course of CornerStone® units on top of the lower units and geogrid at a half bond
  • The two SecureLugs will fit securely into the hollow cores of the two units below and lock the geogrid into the gravel core
  • Pull the unit forward to engage and align the SecureLugs
  • Complete the installation of units on the Geogrid Reinforced courses
  • Make sure each unit is installed against the next unit leaving no gaps between unit joints
  • Tension the geogrid in such a way as NOT to disturb the alignment of the upper units
  • Use stakes or backfill materials to maintain the tension during backfilling
  • Do not drive equipment directly on top of geogrid

Step 4: Reinforced Backfill

  • Backfill and Compact the Reinforced Zone by placing materials from the back of the wall towards the end of the geogrid
  • Install drainage gravel in the cores and 6″ to 12″ behind the units after placing and compacting backfill materials
  • Install and compact backfill materials in 8″ Lifts until wall is complete

More CornerStone 100 Installation

  •  

Chris2021-09-15T17:07:53-06:00

CornerStone 100 Gravity Retaining Wall Installation

Chris2021-09-15T17:07:53-06:00January 7th, 2016|0 Comments

Gravity (SRW) Cornerstone retaining wall systems are structures lower in height that use the CornerStone® unit weight combined with gravel core infill […]

  •  

Chris2021-09-15T17:07:57-06:00

CornerStone Retaining Wall Block Base Elevation Change

Chris2021-09-15T17:07:57-06:00January 7th, 2016|0 Comments

CornerStone Retaining Wall Block Installation For Base Elevation Change are often required and can be problematic if not planned properly. Correct con […]

  •  

Chris2021-09-15T17:07:58-06:00

Retaining Wall Curve CornerStone 100

Chris2021-09-15T17:07:58-06:00January 7th, 2016|0 Comments

Retaining Wall Curve details are often required for specific sites and can be specified by designers and engineers. Correct construction and professio […]

  •  

Chris2021-09-15T17:07:59-06:00

Retaining Wall Corner Installation

Chris2021-09-15T17:07:59-06:00January 7th, 2016|0 Comments

Retaining wall corner installation details are often required for specific sites and can be specified by designers and engineers. Correct construction […]

  •  

Chris2021-09-15T17:08:00-06:00

CornerStone 100 Stairs

Chris2021-09-15T17:08:00-06:00January 7th, 2016|0 Comments

Proper installation of stairs in a wall project requires the same care and thoroughness as the creation of the wall itself. CornerStone’s design featu […]

  •  

Chris2022-02-18T11:35:31-07:00

CornerStone 100 Pillars

Chris2022-02-18T11:35:31-07:00January 7th, 2016|0 Comments

Pillars add a finishing touch of elegance to any CornerStone® wall project. They can be used to create distinguished entranceways to any residence or […]

By Chris|2021-09-15T17:07:55-06:00January 7th, 2016|CornerStone 100, Geogrid Wall, How To, Installation|

Share This Story, Choose Your Platform!

FacebookTwitterRedditLinkedInTumblrPinterestVkEmail

  •  

    Tall CornerStone Retaining Wall Helps Develop Commercial Infrastructure

    July 7th, 2021

  •  

    Bottling Plant Apartments’ Retaining Walls

    February 22nd, 2021

  •  

    CornerStone 100 Gravity Retaining Wall Installation

    January 7th, 2016

  •  

    StoneLedge Base Elevation Change

    January 16th, 2016

  •  

    CornerStone Retaining Wall Block Base Elevation Change

    January 7th, 2016

  •  

    Retaining Wall Curve CornerStone 100

    January 7th, 2016

  •  

    Retaining Wall Corner Installation

    January 7th, 2016

  •  

    CornerStone 100 Stairs

    January 7th, 2016

  •  

    How To Build StoneLedge StoneVista Pillars

    January 17th, 2016

  •  

    CornerStone 100 Pillars

    January 7th, 2016